How long can scaffolding be left up for?

The Health and Safety Executive states that scaffolding must only be left up for as long as it needed and should be removed promptly at the end of the project.

It must also be inspected before it is used for the first time, then every seven days or following any bad weather including storms. If any alterations to the scaffold are needed, then these should also be checked before use.